EnergHys takes next step towards green hydrogen production in Vlissingen-Oost
The large-scale green hydrogen project EnergHys (Joint Venture of TotalEnergies and Air Liquide) in Vlissingen-Oost has advanced a step in the permitting procedure. The Province of Zeeland announced on November 17 that it intends to grant the environmental permit for the hydrogen plant. A permit had already been issued earlier for the excavation work required to prepare the site.
Hydrogen for industry
EnergHys is located within the North Sea Port area, close to the offshore wind energy landing points at Borssele. Zeeland Refinery is situated directly next to the planned installation and is a key intended customer for the hydrogen. Renewable hydrogen can replace a portion of the current hydrogen from fossil sources there. The location also offers opportunities for supply to other industrial customers. A future connection to the regional hydrogen network is intended to increase sales opportunities and further scaling up.
The planned 250 MW electrolyzer, scheduled to be operational in 2029, will produce up to 22,000 tonnes of green hydrogen annually. The majority of this is destined for Zeeland Refinery, of which TotalEnergies is a 55% owner. Through the use of green hydrogen in the refining process, the refinery's CO₂ emissions can be reduced by up to 300,000 tonnes per year. EnergHys is receiving €75 million from the European Innovation Fund. TotalEnergies and Air Liquide are investing €600 million.
Permits and preparation
The application for the environmental permit for the electrolyzer was submitted on 18 May 2026. On 11 November 2026, the Province of Zeeland granted a permit for the necessary excavation works. On 17 November, the intention to also grant the permit for the hydrogen plant followed. The draft decision is available for inspection up to and including 28 December 2026.
- Location: Vlissingen-Oost, North Sea Port
- Initiators: TotalEnergies and Air Liquide
- Electrolysis capacity: 250 MW
- Targeted production: up to 22,000 tonnes of renewable hydrogen per year
- Major customer: Zeeland Refinery
- European contribution: €75 million from the Innovation Fund
- Own investment: €600 million
- Commissioning: scheduled for 2029
- Infrastructure: future connection to the regional hydrogen network
- Permitting status: excavation permit granted; draft decision for the hydrogen plant published